The Washington Times
  • Subscribe
  • Times News Services
  • RSS
  • Mobile Headlines
  • e-edition
  • E-MAIL ALERTS
  • REGISTER
  • LOG IN
  • E-MAIL ALERTS
  • WELCOME
  • Your Profile
  • Log Out
  • Front Page Image
  • Classifieds
  • Autos
  • Real Estate
  • Jobs
  • Special Sections
  • Customer Service
  • Home
  • News
  • Opinion
  • Sports
    • NFL
    • NBA/WNBA
    • MLB
    • NHL
    • Tennis
    • Golf
    • Motorsports
    • Soccer
    • NCAA
    • Olympics
    • Outdoors
    • Other
  • Culture
    • Home & Living
    • Family & Kids
    • Fashion
    • Food
    • Travel
    • Health
    • Washington Visitors
    • Books
    • Military History
    • Life
    • Auto
    • TV Listings
    • Movie Listings
    • Death Notices
    • Entertainment
  • Themes
  • Communities
  • Marketplace
    • Autos
    • Jobs
    • Real Estate
    • Classifieds
    • Shopping
    • Dining Out
    • Education
    • TWT Store
  • Videos
    • Two Guys
    • Birnbaum on Washington
    • Liz Glover
    • Amanda Carpenter
    • Morning Briefing
    • Documentaries
    • Joe Giganti
    • Video Game Minute
  • Podcasts
    • About Headlines
    • Audio and Radio
    • America's Morning News
  • World

    EXCLUSIVE: Iran advocacy group said to skirt lobby rules

  • Security

    Obama said to want revised Afghan options

  • Politics

    Bush warns of threats to freedom, economic growth

  • National

    Fort Hood shooting suspect charged with murder

  • Politics

    Obama has fences to mend on Japan trip

  • Business

    Obama calls for jobs forum in December

  • National

    HOLMES: Miscalculating engagement

Monday, April 3, 2006

Audit reveals school project in Northwest overdue, costly

Rate this story

Average 0.00
after 0 votes
Login or register to rate this story

  • Font Size -+
  • Print
  • Email
  • Comment
  • Tweet this!
  • Share
  • Article
  • Comments ()
  • Click-2-Listen
  • Videos

More Stories

  • Obama begins delicate mission to Japan
  • 'Balloon boy' parents set to plead guilty
  • Spitzer declines to blame politics for downfall
  • Bishop, Kennedy spar over abortion

By

A recent government audit has found millions of dollars in cost overruns and months of delays in the construction of Barnard Elementary School by the D.C. public school system and the U.S. Army Corps of Engineers.

Though the project was supposed to cost $17.1 million and be finished by September 2002 under a fixed-price contract, the school at 430 Decatur St. NW did not open until January 2003 and ended up costing closer to $21 million, according to the D.C. Office of the Inspector General.

Inspector General Charles J. Willoughby's audit, which was issued in final draft on March 23, says the Barnard construction "was not completed by the established deadline, and the project experienced over a 20 percent cost growth, amounting to more than $3.5 million."

Cost estimates for the project were based on specifications that were only 75 percent complete, so officials had to issue 77 contract modifications that totaled $3.5 million to cover work not in the original estimate, according to the report.

The project was fast-tracked with incomplete designs partly because the school system insisted on building the school in 21 months, when the average school construction project usually takes about 30 months, officials said.

The Army Corps defended its handling of the project.

District engineer Col. Robert J. Davis said D.C. school officials insisted on a "deliberately aggressive" construction timeline. He said the Army Corps warned school officials that their schedule could result in a 20 percent increase in construction costs.

"In weighing this cost risk in balance with other objectives, DCPS leadership at the time considered these risks acceptable in the interest of pursuing an aggressive schedule for project completion," Col. Davis wrote.

The school system requested help from the Army Corps in 1998 to manage its capital-improvement program as building conditions worsened. The Barnard project was one of several capital projects overseen by the Army Corps.

The partnership with the Army Corps "was essential to DCPS during a period of instability, characterized by high personnel turnover," including five directors for the school system's Office of Facilities Management in six years, the audit stated.

Col. Davis also said the project complied with federal contracting rules because it is not unusual for the government to award design and construction contracts for projects in which technical specifications are only 35 percent complete. In the case of Barnard, he stated that designs were 80 percent finished.

D.C. Schools Superintendent Clifford B. Janey, in a letter to Mr. Willoughby, said he agrees with the reports findings.

"DCPS has substantially changed its process to minimize the possibility that the conditions noted by the Inspector General's staff will reoccur in future projects," Mr. Janey wrote.

Post a comment

There are comments on this article, submit your opinion!

Commenting is disabled for this entry.
If you feel there is still something worth mentioning about this entry please contact the author or the site admin.

Ask a Question

You Report

Do you have another point of view, photos, audio, video or more information about a story?

Top Stories

Most Read

  1. KELLNER: New Apple mouse really is 'Magic'
  2. D.C. sniper executed in Virginia
  3. Airport rules changed after Ron Paul aide detained
  4. EXCLUSIVE: Warner: Obama misplayed health care debate
  5. Michigan farm expert opens Marijuana U.
More Top Stories »
  1. EXCLUSIVE: Fort Hood suspect contacted Muslim extremists
  2. Houston sheriffs round up thousands of illegals
  3. Tax penalties and prison
  4. PRUDEN: Fatal reluctance to see evil
  5. DeMint tries to ban 'permanent politicians'

Most Shared

  1. KELLNER: New Apple mouse really is 'Magic'
  2. Houston sheriffs round up thousands of illegals
  3. EXCLUSIVE: Fort Hood suspect contacted Muslim extremists
  4. Tax penalties and prison
  5. EDITORIAL: When the shooter becomes the victim
More Top Stories »
  1. Jordanian sees Jerusalem as a powder keg
  2. EDITORIAL: End Clinton-era military base gun ban
  3. Obama's union drive stumbles in N.H.
  4. Employers offer pet health care as perk
  5. E pluribus diversity?

Most Commented

  1. Houston sheriffs round up thousands of illegals
  2. EXCLUSIVE: Fort Hood suspect contacted Muslim extremists
  3. DeMint tries to ban 'permanent politicians'
  4. Obama: 'No faith justifies' Fort Hood attack
  5. Kennedy's disability plan could snag health bill
More Top Stories »
  1. D.C. sniper executed in Virginia
  2. Airport rules changed after Ron Paul aide detained
  3. EXCLUSIVE: GOPer Cao: Health vote may end career
  4. Dobbs leaves CNN before contract ends
  5. EDITORIAL: End Clinton-era military base gun ban

Listen to Washington Times Radio

  • America's Morning News

    with John McCaslin and Melanie Morgan

Blogs & Columns

  • POTUS Notes

    New Dem talking point on Obama approval doesn't wash

  • The Back Story

    12 arrested at Pelosi's office

  • Belief Blog

    New Vatican constitution released

  • Out of Context

    Foods that might kill libido

  • Technology

    Facebook wins round against phishing spammer

  • On the Fly

    United lifts some 'award' blocking

  • Redskins 360

    Nolan prefers chess to coaching

  • Tara's Two Cents

    On their way to summer vacation..

  • SNOBlog

    Beyond 'Woody'

Videos

Advertising Links
TWT Store
  • e-edition
  • Print Edition
  • Weekly Washington Times
TWT Affiliates
  • Middle East Times
  • Golf
  • UPI
  • Arbor Ballroom
  • Washington Times Global
  • About TWT
  • Press Room
  • F.A.Q.
  • Work for TWT
  • Advertise
  • Sponsors
  • Contact Us
  • Privacy Policy
  • Site Map

All site contents © Copyright 2009 The Washington Times, LLC.