- The Washington Times - Monday, August 6, 2007

MINNEAPOLIS (AP) — A plan to replace the bridge that collapsed into the Mississippi River last week is on the fastest of fast tracks: State officials want the span open by the end of next year, and contractors interested in the job must contact the state by dawn Wednesday.

State officials have an ambitious schedule to award contracts to replace the bridge next month, even as search crews remained stymied in their efforts to recover at least eight missing victims from the depths of the Mississippi River. Five people are confirmed dead.

A brutal winter could throw the state’s rapid reconstruction schedule off. But other conditions are favorable — including a construction industry with plenty of available resources to take on such a daunting challenge.

“It is doable. It is a bit fast, but this is an emergency,” said Khaled Mahmoud with the Bridge Engineering Association in New York. “And if we are ever good at anything, it’s responding to emergencies.”

It took only seconds Wednesday night for the eight-lane, 1,900-foot steel truss Interstate 35W bridge, which opened in 1967, to collapse. Three days later, the state had already begun looking for companies interested in erecting a new bridge in just 16 months.

Erecting a new bridge like Minneapolis’ would ordinarily take about three years, even if the design and building phases were overlapped to save time, said Bill Cox, owner of Corman Construction Inc. in Annapolis Junction, Md., a road and bridge construction firm.

Teams of designers and builders are racing to meet the first hurdle, showing they are qualified to bid, said Dick Stehly of American Engineering Testing of St. Paul, which is seeking a role in soil engineering and quality control.

“This is going to be state-of-the-art type of building, which is rapid but also very, very safe and sound,” he said.

The goal of awarding contracts in mid-September is highly ambitious given the array of questions to be answered, including whether to mimic the former bridge’s alignment, how much traffic to accommodate, how much to spend and what it will look like.

“We have committed ourselves to getting it done quickly, but we have also committed ourselves to not getting it done in a way that it is obsolete the day it opens,” Minneapolis Mayor R.T. Rybak he said.

As suppliers are being asked to free up steel, rebar and other key components, state transportation officials warn other projects may languish if a new bridge is to be standing by the end of 2008.

“With an accelerated construction project, you’re going to pay for the acceleration,” said Jon Chiglo, bridge reconstruction project manager for the state Department of Transportation. “There’s definitely impacts to the rest of the system in the area. It’s important to us to get the bridge back in service.”

The new bridge’s design will largely determine the cost, and although the federal government has pledged $250 million, Mahmoud said $300 million to $350 million “sounds about right.”

Federal money for emergency reconstruction of the bridge is primarily meant for replacement of what was lost, along with some reasonable accommodation for increased traffic, said Bob McFarlin, spokesman for Minnesota’s transportation department.

So if the state wants to include some upgrades — like another exit for downtown, better access to the University of Minnesota campus, and features that would make it a landmark showpiece — it may have to pay for them itself.

Story Continues →