Mayor defends New Orleans after Super Bowl outage

Superdome commission records show a $513,250 contract to replace feeder cables was awarded to Louisiana-based Allstar Electric. Arthur Westbrook, Allstar’s project manager for the job, referred all questions to the management company.

A lawyer for the LSED, Larry Roedel, said a preliminary investigation found the replacement work in December did not appear to have caused Sunday’s outage.

And meters showed the 76,000-seat stadium was drawing no more electricity than it does during a typical New Orleans Saints game, according to Doug Thornton, vice president for the Superdome’s management company, SMG

He also ruled out Beyonce’s halftime performance. She brought her own generator.

Officials with the utility and the Superdome were quick to note that an NFL game, the Sugar Bowl and the New Orleans Bowl also were played there in recent weeks.

Both Entergy and SMG said Sunday that an “abnormality” occurred where stadium equipment intersects with an Entergy electric feed, causing a breaker to create the outage. It remained unclear what the abnormality was or why it occurred.