- Associated Press - Sunday, April 27, 2014

COLUMBUS, Miss. (AP) - Maranatha Faith Center Pastor Steve Jamison sees the $5.15 billion settlement from Anadarko Petroleum Corporation as a major turning point in the 15-year fight his East Columbus church has led to remediate the contamination from the former Kerr-McGee site and protect the safety of those who live near it.

The site has been handed over from the Environmental Protection Agency to Multistate Environmental Response Trust and nearly $68 million of that settlement will be used to clean up the 90-acre site that was shut down in 2003, as well as other places where creosote is located.

Regular exposure to creosote, a wood preservative used extensively at the plant while it was in operation, was determined to be carcinogenic to humans by the International Agency for Research on Cancer.

The details of the cleanup plan take 18-24 months to develop through an investigation of the extent and range of the contamination and another six months of EPA review before the process can take place.

Jamison established the Memphis Town Community Action Group in 2012 to work with EPA and expedite the process of cleaning the affected land.

He said the $68 million will be helpful in finally addressing a problem that has been a major health and safety issue in the East Columbus neighborhood, but believes more may be needed and that the overall settlement was paltry considering the hundreds of former Kerr-McGee sites across the country that have similar issues.

In December, the U.S. Bankruptcy Court for the Southern District of New York found Kerr-McGee liable for environmental contamination worth anywhere from $5.2 billion to $14.2 billion. The U.S. Department of Justice and EPA, which filed the suit, settled for the $5.15 billion from Anadarko, which bought Kerr-McGee’s major assets in 2006.

“It’s just underfunded,” Jamison said. “For the damage Kerr-McGee did to Columbus and other areas across the nation, I think the federal government let Kerr-McGee off with a slap on the wrist. No one was made whole but Kerr-McGee.”

Multistate was created in 2011 when the EPA designated the Columbus location as a Superfund site. Cynthia Brooks, company president, said Multistate is managing 23 other sites similar to the one in Columbus as well as more than 400 other smaller ones.

“We step in and take ownership of the hazardous waste sites when there are problems with the owner, either because they’re bankrupt or a site has been orphaned and nobody wants to own it for all the obvious reasons.

“Our priorities are the protection of public health and the environment. We own, manage and clean up these sites to help facilitate their redevelopment and long-term stewardships.

“Governmental or private entities will be taking on ownership and hopefully productive reuse of the sites we’re responsible for. We are very interested in and concerned about what the communities want to see happen at these sites,” Brooks said.

As for the Columbus site, the actual work itself will probably take place over several years, Brooks said.

However, work on remediating the 14th Avenue drainage ditch, which is considered a separate project, is in the design process now and construction will begin this year, she said, and should be wrapped up in 2015. It will include widening the road to accommodate heavy trucks and equipment.

“Site investigation is needed to characterize the nature and extent of the contamination to understand how big the problem is and how far off site it has come to reside.

Story Continues →