LAS VEGAS (AP) | The federal government’s top land steward said Monday that the United States will fast-track efforts to build solar power generating facilities on public space in six western states.

Interior Secretary Ken Salazar said he has signed an order setting aside more than 1,000 square miles of public land for two years of study and environmental reviews to determine where solar power stations should be built.

“We are putting a bull’s-eye on the development of solar energy on our public lands,” Mr. Salazar said during an announcement with Sen. Harry Reid of Nevada in a courtyard shaded by a solar power array at the University of Nevada, Las Vegas.

Mr. Salazar and Mr. Reid, the Democratic Senate majority leader, invoked President Obama’s call for rapid development of renewable energy.

“We hear a lot about doing something about the environment,” said Mr. Reid. “That’s what this is all about. We want to not be dependent on foreign oil. This will make America a more secure nation.”

Mr. Salazar vowed to have 13 “commercial-scale” solar projects under construction by the end of 2010. He set a goal of producing a total of 100,000 megawatts of solar electricity.

Mr. Salazar said the federal Bureau of Land Management (BLM) plans to spend $22 million conducting studies of 24 tracts in the 670,000 acres of property he set aside in Nevada, Arizona, California, Colorado, Utah and New Mexico. Posters displayed Monday showed some of the sites, in southern Nevada; Southern California east of San Diego; an area west of Phoenix; and tracts north of Cedar City in Utah, southwest of Pueblo, Colo., and around Las Cruces, N.M.

Bureau officials said the goal will be to identify lands of at least 3 square miles with solar exposure, suitable slopes and proximity to existing or designated roads and transmission lines. Wilderness, high-conservation-value lands and lands with conflicting uses were excluded. Setting aside the sites, called Solar Energy Study Areas, would prevent new mining claims and other third-party use during the studies.

An industry official hailed Mr. Salazar’s promise to clear a logjam in utility-scale solar developments. The BLM said it has 158 active applications for solar power plants pending.

“In 2007, more than 7,000 permits on BLM lands were approved for oil and gas energy developers,” Solar Energy Industries Association chief Rhone Resch said. “To date, zero permits have been approved for solar energy projects.”

Natural Resources Defense Council analyst Helen O’Shea called the plan to find places for solar arrays “the right path to addressing the climate crisis while protecting our natural heritage and creating much-needed jobs.”

Mr. Salazar said the bureau already was considering environmental reviews for two projects in Nevada: The NextLight Silver State South would have a solar array producing 267 megawatts; the NextLight Silver State North would produce about 140 megawatts.

Copyright © 2018 The Washington Times, LLC. Click here for reprint permission.

The Washington Times Comment Policy

The Washington Times is switching its third-party commenting system from Disqus to Spot.IM. You will need to either create an account with Spot.im or if you wish to use your Disqus account look under the Conversation for the link "Have a Disqus Account?". Please read our Comment Policy before commenting.

 

Click to Read More

Click to Hide