- Associated Press - Wednesday, February 5, 2014

ST. LOUIS (AP) - It will take longer than expected to complete a $380 million renovation project on the Gateway Arch in St. Louis.

The St. Louis Post-Dispatch reports (https://bit.ly/1fuin6a ) a construction schedule released Tuesday says the project is not expected to be completed until the end of December 2016.

Project supporters had hoped to finish the renovation by the Arch’s 50th anniversary in October of 2015. A six-month delay was announced last fall.

The National Park Service’s new timetable includes a one month delay for the park over Interstate 70, five months for the Arch grounds’ north park and seven more months for the south park. A renovation of the bathrooms in the museum under the Arch will be the last component finished.

___

Information from: St. Louis Post-Dispatch, https://www.stltoday.com

Copyright © 2018 The Washington Times, LLC.

The Washington Times Comment Policy

The Washington Times is switching its third-party commenting system from Disqus to Spot.IM. You will need to either create an account with Spot.im or if you wish to use your Disqus account look under the Conversation for the link "Have a Disqus Account?". Please read our Comment Policy before commenting.

 

Click to Read More

Click to Hide