SEATTLE (AP) - Crews have found damage in the seal system that protects the core components of the world’s largest tunneling machine, and officials said Friday they’re still assessing the best way to get the machine helping build a new highway tunnel under Seattle moving again.

It’s unclear when operations can resume. The machine has been mostly idle for two months, raising increased concerns that the troubled project will bust its $1.4 state billion budget. The total viaduct replacement is estimated to be a $3.1 billion project.

The machine, named “Bertha,” is only one-tenth of the way toward completing a 1.7-mile tunnel. The tunnel will carry Highway 99 traffic and allow the removal of the aging Alaskan Way Viaduct along the Seattle waterfront.

On Friday, the state Department of Transportation said inspections conducted last month found that many of the cutter-head openings were clogged with dirt and other things. In a statement, state transportation officials said that late last month they also discovered the seal system protecting Bertha’s main bearing was damaged. This was revealed after “higher-than-normal heat sensor readings” appeared.

“The main bearing is what allows the cutter head to spin,” the statement said, adding the tunnel contractor and experts are working with the Bertha’s manufacturer to try to figure out how to fix the problem.

On a conference call with reporters, Todd Trepanier, the state transportation department’s administrator for the Alaskan Way Viaduct replacement program, said it was too soon to say what effect Bertha’s problems would have on Bertha’s price tag.

“Anything about costs would be speculation,” he said.

In 2009, the Legislature approved the tunnel replacement. But they included a provision in the law requiring Seattle to pay for any cost overruns. Legal experts have said enforcing that requirement would be difficult, noting that the language of the amendment was vague.

Transportation Secretary Lynn Peterson has noted that there’s a $200 million risk-reserve fund for the tunnel. The tunnel project is supposed to be finished in late 2015.

Associated Press writer Mike Baker contributed to this report.

Copyright © 2018 The Washington Times, LLC.

The Washington Times Comment Policy

The Washington Times is switching its third-party commenting system from Disqus to Spot.IM. You will need to either create an account with Spot.im or if you wish to use your Disqus account look under the Conversation for the link "Have a Disqus Account?". Please read our Comment Policy before commenting.

 

Click to Read More and View Comments

Click to Hide