- Associated Press - Tuesday, June 2, 2015

ALEXANDRIA, La. (AP) - The demolition phase of the Rapides Parish Coliseum renovation project is nearly finished, and officials are now hoping for good weather for the upcoming construction phase.

The Town Talk reports (https://townta.lk/1eM5ydb) Bill Tudor of Alliance Design Group told Rapides Parish police jurors Monday that wet weather during certain times of the construction phase could throw off the schedule and add to the cost.

Tudor, whose firm is overseeing the project, updated jurors on the work taking place as part of the $22.9 million renovation project.

Tudor told jurors that the demolition phase is about 85 to 90 percent complete.

___

Information from: Alexandria Daily Town Talk, https://www.thetowntalk.com

Copyright © 2018 The Washington Times, LLC.

The Washington Times Comment Policy

The Washington Times is switching its third-party commenting system from Disqus to Spot.IM. You will need to either create an account with Spot.im or if you wish to use your Disqus account look under the Conversation for the link "Have a Disqus Account?". Please read our Comment Policy before commenting.

 

Click to Read More and View Comments

Click to Hide