- Associated Press - Monday, March 30, 2015

SEATTLE (AP) - Crews have lifted the scuffed and rusty disc-shaped front end of the broken tunnel-boring machine called Bertha from the ground in Seattle, hauling it out of a 120-foot-deep pit so it can be repaired.

The Seattle Times reports (https://is.gd/DdNjhj ) the process seemed to go smoothly, with the 2,000-ton machine segment emerging from the ground Monday.

A Washington state Transportation Department official, Matt Preedy, praised the Dutch lift company involved, as well as contractor Seattle Tunnel Partners and machine maker Hitachi for devising a good lifting plan and carrying it out.

Bertha broke down in December as it worked to build a tunnel under Seattle to replace the Alaskan Way Viaduct — damaged in a 2001 earthquake. The contractor hopes to start drilling again in August.

___



Information from: The Seattle Times, https://www.seattletimes.com

Sign up for Daily Newsletters

Manage Newsletters

Copyright © 2020 The Washington Times, LLC.

Please read our comment policy before commenting.

 

Click to Read More and View Comments

Click to Hide