- Associated Press - Monday, February 29, 2016

FRANKLIN, N.H. (AP) - Officials say plans to build an 8.5-megawatt solar project in Merrimack County can’t proceed until more people are allowed to net meter.

Franklin Mayor Ken Merrifield tells the Concord Monitor (https://bit.ly/1XV6mgK ) that the solar installation, slated to become the largest in the state, would help halve the city’s electric bill.

The project has received municipal approval, but Merrifield says the project is made financially viable through net metering, which lets customers sell excess solar power back into the grid.

Lawmakers are considering legislation that would double the sate-set cap to 100 megawatts and require the Public Utilities Commission to review current net metering rates.

While some say the bill doesn’t go far enough, opponents say solar customers don’t pay enough for pole and wire maintenance due to net metering.

___

Information from: Concord Monitor, https://www.cmonitor.com

Copyright © 2018 The Washington Times, LLC.

The Washington Times Comment Policy

The Washington Times is switching its third-party commenting system from Disqus to Spot.IM. You will need to either create an account with Spot.im or if you wish to use your Disqus account look under the Conversation for the link "Have a Disqus Account?". Please read our Comment Policy before commenting.

 

Click to Read More and View Comments

Click to Hide