PUEBLO, Colo. (AP) - The Army says a plant that will destroy the nation’s largest remaining stockpile of mustard agent won’t start operating until September instead of this spring as planned.

Officials said Thursday that mechanical problems cropped up during tests at the Pueblo Chemical Depot outside Pueblo.

The $4.5 billion plant will disassemble and neutralize 780,000 shells containing 2,600 U.S. tons of the chemical weapon. The Army says the delay was caused by leaks and vibration in pumps, as well as steam-injection problems.

The complex plant will use water to neutralize the mustard agent and then add bacteria to digest and convert the remaining chemicals. The end product can be disposed of at a hazardous waste dump.

The weapons are being destroyed under international treaty.

Copyright © 2018 The Washington Times, LLC.

The Washington Times Comment Policy

The Washington Times is switching its third-party commenting system from Disqus to Spot.IM. You will need to either create an account with Spot.im or if you wish to use your Disqus account look under the Conversation for the link "Have a Disqus Account?". Please read our Comment Policy before commenting.

 

Click to Read More

Click to Hide