- Associated Press - Thursday, April 17, 2014

PORTLAND, Ore. (AP) - The Washington auditor’s office questions $17 million of the $188 million the state spent on plans to build a new Interstate 5 bridge across the Columbia River before the project was aborted.

The audit says most of the money that went to about 30 subcontractors could have been acceptable but they did not submit proper overhead and profit documentation to the general contractor.

The Oregonian reports (https://is.gd/OU12ij ) the Washington Legislature called for the audit.

Washington backed out of the $3.5 billion Columbia River Crossing project last year. Oregon attempted to keep it going on its own, but the project died when the legislative session ended in March.

___

Information from: The Oregonian, https://www.oregonlive.com

Copyright © 2018 The Washington Times, LLC.

The Washington Times Comment Policy

The Washington Times is switching its third-party commenting system from Disqus to Spot.IM. You will need to either create an account with Spot.im or if you wish to use your Disqus account look under the Conversation for the link "Have a Disqus Account?". Please read our Comment Policy before commenting.

 

Click to Read More

Click to Hide