- Associated Press - Monday, June 12, 2017

RUTLAND, Vt. (AP) - The Vermont Electric Power Co. has been granted a land use permit to build a $9.2 million data center in Rutland Town.

The Rutland Herald reports (https://bit.ly/2rimcvQ ) that the permit conditions require the company known as VELCO to monitor possible negative impacts on neighbors from the blasting, such as to foundations and wells.

The nearly 7,000-square-foot data center will house the company’s weather analytics system and other computers. Three neighbors of the parcel had asked for a full land use hearing on the project saying their wells had been negatively impacted by earlier VELCO projects.

According to emails filed with the District 1 Environmental Commission, the neighbors then met with VELCO officials and worked out an agreement for testing.


Copyright © 2018 The Washington Times, LLC.

The Washington Times Comment Policy

The Washington Times welcomes your comments on Spot.im, our third-party provider. Please read our Comment Policy before commenting.

 

Click to Read More and View Comments