MINOT, N.D. (AP) - The city of Minot has hired a Minneapolis law firm to look at legal options regarding two problem-plagued downtown parking ramps.

The city has spent millions more than intended on the Renaissance ramp and the Central ramp, and contractors are behind in completing exterior and alley work.

The ramps opened in 2016 after years of construction marked by contractor disputes and delays. The original bid was $10.5 million, but the ramps ended up costing nearly double that.

City Manager Tom Barry tells KXMC-TV that no legal action has begun, but he considers legal representation critical to protecting the city’s investment. He told the City Council earlier this month that the contractor is balking at finishing the structures as originally designed.


Copyright © 2018 The Washington Times, LLC.

The Washington Times Comment Policy

The Washington Times welcomes your comments on Spot.im, our third-party provider. Please read our Comment Policy before commenting.

 

Click to Read More and View Comments

Click to Hide