- The Washington Times - Wednesday, October 1, 2008

— The glittering, steel-and-glass domed rail hub had seemed for years to be the only thing that was going right at ground zero.

Lately, not so much.

The World Trade Center rail station - a planned architectural masterpiece with steel ribs jutting like a bird’s wings from the dome, a retractable skylight and a vast, naturally lighted concourse - is hundreds of millions of dollars over budget and five years behind schedule.

The delays are creating a domino effect, slowing construction of the Sept. 11 memorial and most other projects on the problem-ridden 16-acre site.

The Port Authority of New York and New Jersey, the owners of ground zero and the agency building the hub, is expected to announce another redesign of the project this week along with new cost estimates that put the price tag at about $3 billion, more than $500 million over its original budget.



But reports prepared for the federal government - which is funding the terminal with post-Sept. 11 money - show that problems managing the project were foreseen at least two years ago.

The transportation consultant reports warned of management problems, cost overruns and delays at the hub going back to 2006, less than a year after construction began.

The rail terminal would replace a PATH commuter rail hub that was underneath the trade center’s twin towers before Sept. 11, 2001, and a temporary station that opened in 2003. The PATH trains take commuters between New York and New Jersey.

The design by Spanish architect New York Times architecture review in 2004, and perhaps a more moving Sept. 11 tribute than the memorial.

The hub would include high-end shops and underground concourses connecting passengers to more than a dozen subway lines. Business leaders have said the terminal would attract corporate tenants to the five planned skyscrapers and the financial district.

Because the hub is located in the middle of ground zero, its problems affect a maze of interconnected skyscrapers, the memorial, city streets and vehicle security center planned for the site.

The federal consultant reports assessing risks on the project are prepared every three months for the Federal Transit Administration, which funded the hub with an initial $1.9 billion grant.

In July 2006, the report by the Carter & Burgess consultants concluded the hub had less than a 10 percent chance of being on budget. Every three months, the consultants issued new reports that estimated delays as high as 15 months.

By early 2008, the consultants said it was less than 5 percent likely to be on budget.

Failure to make timely decisions, delays in procuring contractors, constant design changes and the extra cost of paying staff for a longer-than-expected job were repeatedly cited as indicators of budget and schedule problems in 18 months of reports reviewed by the Associated Press after a Freedom of Information Act request.

“This is a large, schedule-driven project with an aggressive design schedule,” the report read in July 2006, referring to “rushed,” incomplete design documents that were causing delays.

Analysts said the reports show longtime oversight problems at the complicated project. “It probably does raise some red flags,” said Regional Plan Association.

Port Authority spokesman Stephen Sigmund said the agency acknowledged problems with the project in a June report, “and have since moved forward with a new way of doing business on the site in close coordination with the [federal government] and other partners. And we are producing positive results.”

Sign up for Daily Newsletters

Manage Newsletters

Copyright © 2020 The Washington Times, LLC. Click here for reprint permission.

Please read our comment policy before commenting.

 

Click to Read More and View Comments

Click to Hide