- Associated Press - Monday, January 13, 2014

HUNTINGTON, W.Va. (AP) - Construction of the roof for Marshall University’s new indoor athletic facility is complete, thanks to a helicopter.

Marshall director of facilities and planning Ron May says space confinements prevented using a crane to place panels on the roof’s east side.

May tells the Herald-Dispatch (https://bit.ly/1eOwOBR) that a helicopter was used to place the panels.

The building is expected to be completed by August 2014.

It will house a 120-yard football field, a track and other practice facilities.



___

Information from: The Herald-Dispatch, https://www.herald-dispatch.com

Sign up for Daily Newsletters

Manage Newsletters

Copyright © 2020 The Washington Times, LLC.

Please read our comment policy before commenting.

 

Click to Read More and View Comments

Click to Hide